STC-8716, N 7TH AVE RRX, UPRR, 819455X, PAYETTE
programmed not obligated- Source document
- Idaho approved transportation investment program, FY2027 through FY2033, dated September 26, 2026
- Program
- Idaho Transportation Investment Program, FY2027 through FY2033, Rail-Highway Crossing Program
- Year as reported
- 2029
- Amount, USD
- $900,000
- What the amount covers
- Scheduled CN phase with match in year-of-expenditure dollars; table in $1,000 units; excludes separate PE and RW costs; not an award or obligated amount
FY 2027 - FY 2033 Approved ITIP Hwy Safety - Railroad Crossings Approved 9/17/26 Sponsor Program Fund Ph 2027 2028 2029 2030 2031 2032 2033 PREL Total Federal Match Notes STC-8716, N 7TH AVE RRX, UPRR, 819455X, PAYETTE 3 CN - - 900 - - - - - 900 900 - 24295 MP 0.590 - 0.590 SAFTY/TRAF OPER, Railroad Gates PE - 195 - - - - - - 195 195 - PAYETTE, CITY OF RAIL (L) FED RRX RW - - - - - - - - - - - This project will add bike/pedestrian facilities, improve the crossing surface and adjust the track on N 7th Avenue.
Source note: Project key 24295. The board approved the FY2027 through FY2033 plan on 17 September 2026. This table was generated on 26 September 2026. The amount covers the scheduled CN phase with match in year-of-expenditure dollars. It excludes separate preliminary engineering and right-of-way costs. Separate preliminary engineering is scheduled for FY2028 at $195,000. The plan is subject to revision. It does not establish an award, an obligation or completed construction. Earlier board-packet entries retain their original dates and amounts.